The following actions must be taken prior to working on ___

The following actions must be taken prior to working on a circuit breaker.

Arrange these items in the proper sequence, then select the choice below that lists the events in the proper sequence.

  1. Tag the power switch
  2. Obtain the approval of the electrical officer
  3. Remove power to the circuit breaker
  4. Check the applicable technical manual

A. 1, 2, 3, 4
B. 3, 2, 4, 1
C. 4, 2, 3, 1
D. 2, 1, 4, 3

Show Answer

Answer: C